Authorization to go to bid on Yale Gym Remodel

On May 1 plans were submitted to Cowlitz Building and Planning for permit review.  The full set of construction documents is currently being prepared with the target of bidding the Yale Gym Project in the next two weeks.  Eric Lanciault will review the design with the board and we will be seeking authorization to put the project out to bid.   I have a set of permit documents in my office for review prior to the board meeting should you desire. 

 

Administrative Recommendation /MOTION/ "I move we accept the plan for the Yale Gym remodel and authorize the superintendent to seek bids for the project."

Attached Files:
130510_Yale Gym Bid Overview.pdf application/pdf 8M