Mon Jul 8 2013, 5:00pm
District Meeting Room Portable
Regular Meeting

ACTION ITEMS

Approve Construction change directive for Yale School

In the process of removing underground oil tanks at Yale School leakage from one tank was discovered. This has resulted in additional work that I have authorized.  The expected cost is $10-20k depending on the extent of the plumes.  Acceptance of this CCD is acknowledgement of the board's awareness of the issue and potential cost. 

 
Administrative Recommendation: /MOTION/ I move we accept Yale CCD #1 for cleanup of contaminated soil associated with underground heating oil tank removal. 

 

Attached Files:
CCD- Soil Removal.pdf application/pdf 627K