Acceptance of Value Engineering Report

Attached is the completed Final Value Engineering report for the new WHS project.     In January 2013 the CSG conducted a value engineering study of the plans for the new WHS.  That process resulted in 60 proposals with a net savings value of $5.6 million.   The design team reviewed the VE Teams proposals and agreed to $3.3 million in potential savings.

 

Kelley Wilson of CSG will present the report to the board at the board meeting.

 

Adminsitratvie Recommendation /MOTION/  "I move we accept the Value Engineering Report for the new WHS as presented."