Attached is Change order #29 for Woodland High School. The total amount of the change order is $33,915.
Details:
CCD-149-Free Throw Lines at the Gyms: The orignial striping plan did not include free throuw lines for the side baskets. These were added after the floor was finished.
CCD-150 Repair Cords on OFOI Equipment: Much of the shop equipment was moved from the old shop. We asked the contractor to replace several cords in the interst of student safety.
CCD 151 T&M Wall Porjector in Culinary Arts: We needed to make changes to the dual projector system in culinary arts to accomodate the needs of the instructor.
CCD 152 T&M Electrical Switch Covers: Throughout the school we added lexan covers to switches and control plates.
CCD 157 Robinson Road Cul-D-Sac Grinding and Paving per City of Woodland: There was a significant birdbath in the Cul-D-Sac that needed to be remediated as required by the city.
CCD 158 Accounstical Wall Panels at the Band Room: The accoustics in the band room are far less than optimal. This CCD ads several engineered panels to the walls in the band room to deaden the sound a bit.
COP 88R Modify Light Pole Arm on Dike Access Road: The west most light pole on Dike Access interfered with power lines. the arm on the pole must be shortened so it can be installed.
Adminsitratiive Recommendaiton /MOTION/ "I move we approve Change Order #29 as presented"