REPORTS TO THE BOARD

Maintenance Report

April 19, 2011

 

To: Michael Green
From: Bill Hanson
Re: Maintenance Report

The following are projects that the Maintenance Department has been working on:

  • Had metal put along bottom of Middle School Gym to replace the stucco that was getting large holes torn in it.

  • Had a new auto door put in at High School by pop machine to replace the one that they don't make parts for anymore.

  • Trimmed trees outside the Commons in parking lot.

  • Custodians got all the floors waxed and the schools looking good.

  • Had all the baskets at the Intermediate School welded in the play shed, to help stop them from getting torn down.